Construction Projects

Lab Renovation Bldg. 52

General Service Administration (GSA), Federal Highway Administration BuildinG, Denver Federal Center, Lakewood, co

Project consisted of a complete overhaul consisting of new construction/renovation of a highly technical lab while maintaining daily lab operations in a highly used work environment.  Including overhead doors, epoxy flooring, fire alarm (and commissioning), sprinklers, new metal lockers, overhead vacuum system, and compressed air and gas.

Before HDI could update the outdated section of the facility, asbestos abatement was necessary before installing new mechanical and air handling equipment. To make the area functional, HDI installed an upgraded electrical grid to include main distribution panel, switchgear and transformer. The customer was ecstatic with the finished product!


Huron Cooling Tower Replacement

General Service Administration (GSA), Huron SD

A Design-Build project using a 210-ton crane lifting new cooling towers onto the roof of the Federal Building in Huron, SD. A highly technical project requiring incredible coordination with HDI’s customer(s) from start to finish.  HDI had the in-house experience and a bevy of talented subcontractors to make this happen in minimal time, meeting/exceeding all of the customer’s expectations.  The process included draining the existing system, demolishing the existing cooling tower to include piping, pumps, electrical connections and accessories.  Once completed, during challenging weather conditions HDI lifted, installed and connected two new cooling towers. Consisting of connecting new pumps, electrical reconnects, new chemical system, automated monitoring controls (BAS) system and finally passing the start-up & commissioning flawlessly.


Design-Build Clay Center Modernization, Phase 3

United states department of Agriculture (USDA) Clay Center, NE

Project included the modernization of buildings to include extensive electrical, air handlers, and steam boiler upgrades. HDI began by providing all new transformers to USDA Buildings 1, 2, 17. New primary and secondary feeders were installed to existing power poles in buildings which included new concrete pads and road crossings. This was followed by the removal/replacement of the existing steam boilers and all associate piping and flues in Building 19. The demolition of existing air handlers 1 & 2, were replaced with new roof top units. HDI provided and installed a complete hydronic heating system with the associated piping, gas regulators, heat exchanger, heat pumps with diffusers, balancing kits, expansion tanks, and air separators. Decontamination of the bio safety cabinets prior to their demolition were replaced while HD INC. capped the abandoned exhaust ducts above the hard lid and repaired the drywall ceilings above the existing BSC’s, including painting and then capping of all existing air lines. Finish work included drywall repair with a level 5 finish and painting.


Feed Mill Repairs, Phase 1

United states department of agriculture (USDA), Miles City, MT

HDI designed and accomplished the new construction of the feed mill conveying system on time with minimal changes after construction started.  The new concrete foundation, site work, electrical, lighting protection system, replacement of grain bin controls and electrical power brought the mill conveying system up to current standards and will be productive for long into the future.  The USDA worked closely with HDI throughout the design process until the project completion making this a great success story for the USDA and HDI.


Aspen Airport Traffic Control Tower Roof Replacement

Federal Aviation Administration (Faa), aSPEN, co

An FAA roofing repairs project which included complete repair/sealing of damaged surfaces to the roof membrane.  The damaged surface repair included; repair & reseal damaged flashing, sealing around all windows and metal inserts, new roof drains, and repairing/ resealing moisture intrusion areas for approximately 4,500 sf.


Emergency Vault Repairs

United states department of agriculture, national forest service, colorado state univercity campus, fort collins, co

Project included replacing a 10-ton refrigeration system, compressors, air-cooled condensing units, and evaporators for the USDA Seed Vault to include replacing electrical buckets supporting the demand for the new mechanical equipment. This replacement was considered a national emergency, as these refrigerated seed vaults housed hundreds of thousands of rare seeds for the USDA. Because of this, the entire demolition and replacement of equipment had to be accomplished without taking the existing cooling system offline.  Our people had to wear parkas and restrict time in the freezer to 15 minutes in order to prevent injury.  HDI removed and reclaimed existing refrigerant from the existing chillers to use with the new system. In order to replace the condensing units, HDI used a rigging crane replacing existing condensers one at a time allowing the system stay operational.

Storm Water Basin Repair

center for disease control and prevention, Colorado state univercity campus, Fort Collins, CO

A Design-Build Project that incorporated repairing a water drainage basin eliminating high volumes of seasonal water eroding dirt and distributing silt and mud onto Colorado State University’s (CSU’s) lakeside property. Two steel-reinforced 22’x8’x8” drop wall structures (with footings) were excavated and poured in place.  The structures acted as check damns for seasonal storm surges. During the excavation, proper sloping and benching were used in strict accordance with OSHA guidelines.  Class-B filter material and rip rap was used on the drainage flowline , with a 9 foot 3/1 sloped sidewalls. A center section (approximately 20’ long parallel with the flowline) was compacted, seeded, and blanketed with Turf Reinforcement Mat (TRM) encouraging natural vegetation and limit erosion. Rip rap was used to match existing landscape boulders.  Existing concrete flared end sections and drainage pipe were cleaned of silt/debris which were discharging water onto CSU property.  Hydro mulching was used to reclaim native grasses.


Fraser Lexan Weir Rehab

United states dapartment of agriculture, national forest service, Fraser, CO

Remote project involving the repairing of collapsed sidewalls and recorder hut of a research weir, included the demolition of the existing upper and lower weir walls.  After demolition, over excavating was done on the tilling pond with new corrugated hydrostatic piping. HDI placed a new clay liner in the tilling pond while grading/landscaping the surround grounds.


Raymond Façade Replacement

General Service Administration (GSA), Raymond, MT

Renovation of a 5,000 SF Customs and Border Patrol two-story facility owned by the GSA.  Using Building Information Modeling (BIM), HDI removed three sides of the exterior walls, adding steel, new panels, repairing damp proofing to the foundation, roofing, landscaping, drywall, finned tubes, architectural and mechanical louvers, insulated metal panel exterior, low E windows, electrical upgrades, blinds throughout, and specialized envelope testing.

A challenge HDI overcame during the construction was the remote location, wind and extreme temperatures variances. HDI’s ability to preplan and coordinate these variables into the construction plan brought the facility on time and in budget. 


Bennet Switchgear Replacement

General Services Administration (GSA), Salt Lake City, UT

Project included the replacing of existing switchgear with new upgraded switchgear in the eight-story Bennett Federal Building complex housing several government agencies and two U.S. Senators.  Constant coordination between HDI and the GSA was critical due to the sensitivity and level of clearances in facility.  

The preplanning and coordination between HDI, GSA and building management started early on in the process to ensure the power outage would not interrupt building services during normal working hours. Two 3-day weekends were agreed upon for the scheduled work, with the first weekend for the main-tie-main switchgear at the utility connection and the second weekend selected for the secondary A-B switchgear.  All this work was fast paced, long hours, and constant monitoring to enable the installation, testing, and energizing went off without a hitch, and it did. 

The team effort between the HDI, GSA, and building management with respect to the design, material fabrication and procurement process allowed short duration turn-around times over each three-day weekend making this such a successful project.

Devils Nose Shooting Area

United States Department of agriculture, Idaho Springs, CO

Installation of three shooting shade structures at the Devils Nose Shooting Area located at an elevation of 11,060 in the Roosevelt National Forest.  The work was multi-faceted; consisting of access road construction, roadway re-conditioning, accessible trails, mobilization, earthwork and demolition, blasting, rock and soil processing, timber stairs, and erosion control. 

Shooting shade structures include: structural steel and bracing, connections, steel framing, railings, wood carpentry, engineered lumber, wood sheathing, blocking, metal roofing, finishing. Roofing also included ice and water shields and fascia. 

In addition to storm drainage infrastructure, there are on-site rock walls and concrete walls, site features, landscaping, riprap, slope stabilization, and boulder placement.



Repair Landscaping Bldg. 30

Wyoming Air National Guard (WYANG),Cheyenne, WY

Removed existing wooden fence while keeping the metal and masonry supports in place.  HDI Installed a 4-inch concrete walking pad, removed rock ground cover and replaced with irrigated sod.  Soil excavated to 12 inches below the sidewalk grade, installed six inches of loam fill material, spread four inches of topsoil on top of the fill material and laid sod with new irrigation lines. HDI installed a new four-zone irrigational system connecting to a nearby water box with new electrical conduit.

Air Traffic Control Tower Parking Lot Expansion

Federal Aviation Adminitration, longmont, CO

Remote Air Traffic Control center road rehabilitation to include mobilization, excavation, asphalt pavement repairs, concrete, and drainage repair.  Including demolition of sloped sidewalk with ponding issues, Installation of new asphalt parking spaces and upgrading stormwater flow to existing storm drains. Placed new visitor’s parking lot sidewalk to the Child Care Facility.  Installed ADA compliant concrete ramp, re-work of irrigation system, constructed new sloped sidewalk solving ponding issues and replanting and sodding as necessary. 


Construct Swine Walkway

united states department of agriculture (USDA), Clay Center, NE

Construction of a new 28’ x 40’ wood framed metal sheeted building with concrete floor/foundation with underground utilities from existing building. Purpose of new structure is to facilitate movement and maintain sterilization requirements for the swine.

Building is constructed on a stem wall foundation, with poured in-place concrete flooring. Building includes a wooden frame and metal sheeted exterior with new plumbing, electrical, and HVAC system.  The interior consists of finished office rooms, swine walkway corridor, restroom, and a swine holding area enclosed with fabricated gates and fencing that is equipped with a digital scale.


Bridge 16 Repairs

United states department of agriculture, clay center, ne

Project involved demolition and construction of a new bridge with storm water management (bridge spans over waterway), traffic control, concrete and steel bridge demolition.  HDI exported and disposed of materials, imported new material for embankment construction, installation of new concrete deck planks and installation of guard rail.  HDI completed the bridge project with gravel approaches at both ends. 


Concrete Repair of Facilities Management Division Yard

National Insitute of standards and technology, boulder, co

Storage yard demolition and replacement of an existing concrete pad.  Concrete removed, new class 6 road base brought in and subgrade compacted. Road base laid in eight-inch lifts matching existing concrete edges. Water line placed across an existing roadway. New concrete and asphalt were poured back to the existing conditions with some irrigation line work and restoring the natural area.  Trenching (6’ x 4’) for a new frost-free hydrant was accomplished to connect to an existing storage area.